Trunk pipelines:


Andhra Pradesh State Natural Gas Pipeline Grid

APGDC has been authorized to lay, operate, expand Natural Gas Pipeline from Kakinada to Srikakulam (Total length of the pipeline is around 300 KM) through a bidding process carried out by Petroleum and Natural Gas Regulatory Board (PNGRB) and has already taken up the construction of the pipeline project. APGDC has taken up the project as per schedule drawn in line with business requirements.

• Detail Route Survey work is in progress.
• Project Site Office has been opened at Kakinada.
• Project Management Consultant has been appointed.
• Agreements / Heads of Agreement have been signed for gas transmission for capacity booking in KSPL Pipeline for  13.00 MMSCMD with 11 consumers.
• RoU acquisition work is in progress
• Design basis prepared. Work for EPC award is under progress.
• EoI for booking of capacity in KSPL sought from customers.